Project Overview:

To upgrade and replace the existing 1960’s riser panels with Eaton bespoke-made MCB electrical panels plus replacement of riser supply cables and associated containment.

Scope of Work:

  • Design
  • Metal containment throughout risers
  • New bespoke panels
  • Riser and submain cabling
  • Electrical Instillation Condition Report
  • Remedials following replacement

All-Round Top Job:

This project was completed by G M Monk’s install team out of normal working hours. The engineers were working up to 10 hours per day to ensure disturbance to the buildings normal operations were kept to a minimum. We have had extremely positive feedback from both the client and building users.