Project Description

Scope of Work

  • Carry out design and cable calculations
  • Install supply for new panel board
  • Install external heavy-duty ladder rack

Key Challenges

We initially met with the client to discuss the best way to complete the projects to meet their requirements. We carried out all the design and cable calculations in-house to reduce the costs of external consultants. We installed a 355A supply for the new Eaton MCCB panel board for their new machinery and also installed an external heavy-duty ladder rack as well as a 185mm 4 core SWA cable from the existing Dorman Smith main LV switch panel. All switch panel modifications were done in-house.

We were able to complete the project on time, within budget and in the planned programme of works that included planned shutdowns at the weekend to complete the work.