Project Description

Scope of Work

  • Remove existing sub-main supplies
  • Install new containment system
  • re-install sub-main supplies onto new cable tray

Key Challenges

This Brighton client required a solution for a new containment system along a curved wall taking off existing sub-main supplies and re-instating them onto the new cable tray.

The works had to be completed on a Spider access platform due to the sloped area which added extra obstacles for the team to overcome.